Title 13 WATER AND SEWERS
Chapter 13.36 STANDARDS--PIPELINE INSTALLATIONS
13.36.010 Generally.
13.36.020 Depth of cover.
13.36.030 Laying and handling pipe.
13.36.040 Thrust devices.
13.36.010 Generally.
All piping shall be supported and braced against movement. When temporary
supports are used they shall be sufficiently rigid to prevent any shifting or
distortion of the pipe.
Where piping is installed on curves the maximum
deflection of each joint shall be within the maximum deflection recommended by
the pipe manufacturers.
Sufficient flexible couplings whose design is
approved by the county engineer shall be provided in all piping adjacent to
structures to permit differential settling of the foundation of said piping and
structures without damage to the piping, or as may be required for ease of
installation or removal of the pipe.
All dirt and scale shall be removed
from the pipe prior to installing.
When water, house or building
connections pass under a curb, the curb shall be permanently marked with a
capital W at least two inches high. When connections are installed before curbs
and curbs are to be installed under the same subdivision agreement, the water
line contractor shall reference the connection locations and mark the curbs
after the curb installation. (Ord. 383 § 295, 1974).
13.36.020 Depth of cover.
The minimum depth of cover from finish grade at valve locations within the
rights-of-way shall be as follows:
|
4” - 6” pipe
|
36” to 38”
|
|
8” pipe
|
36” to 42”
|
|
10” pipe
|
40” to 46”
|
|
12” pipe
|
44” to 50”
|
|
14” pipe
|
47” to 53”
|
|
14” or greater pipe
|
as required by the engineer
|
In no case shall cover of pipes be less than thirty-six inches unless
otherwise permitted by the county engineer. (Ord. 383 § 296,
1974).
13.36.030 Laying and handling pipe.
Proper implements, tools and facilities satisfactory to the county
engineer shall be provided and used by the contractor for the safe, convenient
and workmanlike prosecution of the work.
All pipes, fittings and valves
shall be carefully lowered into the trench in such a manner as to prevent damage
to pipe or pipe coating. Under no circumstances shall pipe or accessories be
dropped or dumped into the trench. Before laying, the pipe shall be inspected
for defects and cast iron pipe shall be rung with a light hammer to detect
cracks. Any defective, damaged or unsound pipe shall be rejected and sound
material furnished. Cutting of pipe for inserting valves, fittings, or closure
pieces shall be done in a neat and skillful manner without damage to the
pipe.
All pipe shall be laid and maintained in the required alignment
with fittings and valves at the required locations and with joints centered and
spigots home, and with all valve stems plumb. When the pipe is bedded in a
trench it shall be brought into true alignment and shall be secured there with
proper backfill material, carefully tamped under and on each side of it. Care
shall be taken to prevent dirt from entering the joint
space.
Preparatory to making pipe joints, all surfaces of the portions
of the pipe to be jointed or of the factory-made jointing material shall be
clean and dry. Lubricants, primers, adhesives, etc., shall be used as
recommended by the pipe or joint manufacturer’s specifications. The
jointing or factory fabricated joints shall then be placed, fitted, joined and
adjusted in such a workmanlike manner as to obtain the degree of water tightness
required. As soon as possible after the joint is made, sufficient backfill
material shall be placed along each side of the pipe to offset conditions that
might tend to move the pipe off line and grade.
All trenches and
excavations shall be backfilled immediately after pipe is laid therein, but
leave all the joints exposed until pressure and leakage tests are completed.
Under no circumstances, however, shall water be permitted to rise in
unbackfilled trenches after the pipe has been placed.
Each length of
pipe shall be freed of any visible evidence of contamination, dirt and foreign
material before it is lowered into its position in the trench, and it shall be
kept clean during and after laying. When pipe laying is not in progress, the
open ends of any pipe which has been laid shall be plugged. Trench water shall
not be permitted to enter the pipe.
All installation shall be in full
conformance with the manufacturer’s recommendations. (Ord. 383 §
297, 1974).
13.36.040 Thrust devices.
A reaction or thrust blocking shall be installed at all tees, bends,
plugs, fire hydrants, crosses which have one or more openings plugged, dead-ends
except welded steel pipe and other sections of piping and appurtenances that
might be capable of being displaced by the action of either working pressure or
test pressures within the water system.
The size and type of thrust
devices shall be designated to prevent movement of water mains when subjected to
the maximum hydrostatic test pressure of two hundred psi and not to exceed the
allowable bearing capacity for the supporting soil involved. Thrust devices
shall be cast-in place concrete, metal harness, or other suitable and approved
types.
Temporary bracing must not be restored to for thrust blocking.
The pipe must not be pressure tested before the concrete thrust blocks have
completely set. (Ord. 383 § 298, 1974).
<< previous | next >>