Title 13 WATER AND SEWERS
Chapter 13.39 STANDARDS--PIPELINE EARTHWORK
13.39.010 Trenching.
13.39.020 Bracing.
13.39.030 Water control.
13.39.040 Bedding and backfilling.
13.39.010 Trenching.
Trenching for all pipes shall be in open cut to the lines and grades shown
on the plans, except that sections not to exceed eight feet in length may be in
a tunnel where necessary in the opinion of the county engineer, to protect
existing trees or structures. Where tunnels are required, the roof shall be
sloped forty-five degrees downward from each end. Any paving which is to be
removed shall be scored at or adjacent to the edges of the trench to such a
depth and in such a manner before trenching operations are begun as to avoid
damage to paving outside the trench area during trenching operations. (Ord. 383
§ 310, 1974).
13.39.020 Bracing.
The sides of all excavations shall be supported in the manner set forth in
the “Construction Safety Orders” issued by the Division of
Industrial Safety, Department of Industrial Relations, state of California.
Sheet piling and other timbering shall be withdrawn in such a manner as to
prevent caving of the walls of excavations or damage to piping or other
structures. Whenever timber or other sheeting is driven to a depth below the
elevation of the top of the pipe, that portion of the sheeting below the
elevation of the top of the pipe shall not be disturbed or removed. (Ord. 383
§ 311, 1974).
13.39.030 Water control.
The contractor shall remove all water which may accumulate in the
excavation during the progress of the work so that all work can be in the dry.
Trenches shall be kept free from water while the pipe or other structures are
installed, while concrete is setting and until backfill has progressed to a
sufficient height to anchor the work against possible flotation. (Ord. 383
§ 312, 1974).
13.39.040 Bedding and backfilling.
Bedding for all piping installations shall be sufficient for the loads to
which the pipe may be subjected as determined by the county engineer, but no
less than the minimum herein set forth.
If soil conditions are stable,
and the trench bottom is of a material that can be cut true and straight, pipe
can be installed using the uniform trench bottom for support. Bell holes must be
dug to provide a minimum clearance of two inches below the
couplings.
The trench bottom must be straight, free of bumps or hollows
and at the correct grade. As the pipe is laid, any irregularities in the trench
bottom must be leveled off or filled in with tamped soil.
Where the
trench bottom is in hardpan, rock or any similar unyielding bed, the trench
should be excavated at least six inches below trench grade and then brought back
to grade with selected, tamped soil before laying the pipe.
In unstable
or soft soils, the trench shall be excavated to stable soil and refill with
selected material such as gravel or crushed rock until pipe grade is
reached.
When spreading refill soil on the trench bottom, provide a
minimum clearance of two inches below the coupling.
The initial
backfilling shall be hand-placed to at least twelve inches over the pipe with a
suitable material free of large stones greater than one-half inch diameter and
in cold weather, free of frozen lumps. Backfill material shall be placed in such
a manner as to not injure or disturb the pipe and then thoroughly tamped at
layers of four inches.
The balance of the backfill, which is from twelve
inches over the top of the pipe to finished grade shall have relative compaction
equal to adjacent undisturbed soil, but in no case less than ninety percent.
Backfill material shall be free from too large stones, organic matter or other
deleterious substances. (Ord. 383 § 313, 1974).
<< previous | next >>